The federal government’s watchdog agency says getting NASA’s heavy-lift Space Launch System rocket off the ground is likely to take longer and cost more than the space agency says it will.
Any issues that crop up in the months ahead could push the first uncrewed SLS launch, known as Artemis 1, from its planned mid-2020 timetable to mid-2021, the Government Accountability Office said in a study issued today.
What’s more, the GAO says NASA has been shifting costs forward to make it look as if expenses for the first launch have grown by $1 billion, when the actual adjusted cost growth is $1.8 billion.
Schedule and cost issues for SLS are particularly problematic because the rocket has been selected to carry NASA astronauts to the moon by 2024.